The Granville bridge from Cherry Street to Columbus Road that closed in July for refurbishment was supposed to reopen at the end of this year, but a legal dispute held up construction and it might not reopen until spring.

The bridge over Raccoon Creek and the T.J. Evans bike path was supposed to be closed for 180 days starting July 27 for a $4.5 million renovation that Licking County Engineer Jared Knerr said will extend the life of the structure for another 15 to 25 years. 

Work on the Cherry Street bridge to Columbus Road in Granville continues but was delayed by a lawsuit and is likely to extend into spring 2027. Credit: Alan Miller

But Knerr said Monday that the legal dispute by a contractor who didn’t win the contract for the job resulted in delays that put the project behind schedule.

“They haven’t made enough progress to set an opening date,” Knerr said. “It’s more than likely that it will be spring.”

| Read more: Construction company files lawsuit to stop rehabilitation of Cherry Street / Columbus Road bridge in Granville

Weather is a big factor now. If warm, relatively dry weather were to continue during the next month or two, that would allow work to continue and speed up progress, he said. But the job requires pouring concrete, and that won’t happen in the kind of cold weather that is typical from now until spring.

“We continue to be frustrated with it,” said Granville Village Manager Herb Koehler. “It’s really causing some problems with our traffic downtown and especially on South Main Street.”

He said that because the bridge work is a state and county project, the village has virtually no influence to speed up the progress. And Koehler said village leaders appreciate the community’s patience and their willingness to graciously help each other through the congestion that sometimes develops.

Motorists routinely are seen stopping to allow a fellow motorist to turn left into a business or side street, or stopping traffic in both directions on South Main to allow traffic on Elm Street to cross over Main Street.

“We’re thankful that people are being polite about it, in terms of being sensitive to the congestion it has caused and allowing people to cross over,” Koehler said, adding that village leaders are “hoping the weather will cooperate so that they can reopen the bridge as soon as possible.”

Knerr said the county received federal funds for the project, and the initial single bid for the work was about 25% above the engineer’s estimate, so that bid was rejected and the county advertised for a second round of bids. The low bidder, Suburban Maintenance and Construction of North Royalton, Ohio, got the job.

| Read more: Bridge closed ahead: Granville viaduct repairs will cause 6-month detour

Records in the county engineer’s office indicate the bridge, or “viaduct,” as it is also known, was built around 1930 and underwent repairs in 1964 and 2004.

The need to rebid the project delayed it from the original time frame, which would have seen the project start sooner than July. Then came a lawsuit filed on July 31 by Complete General Construction of Columbus saying that the county improperly awarded the contract to Suburban Maintenance and Construction.

The lawsuit against the Licking County Commissioners and the Ohio Department of Transportation (ODOT) was filed in Licking County Common Pleas Court and transferred to Franklin County Common Pleas Court, where ODOT is headquartered. It is scheduled for trial in September 2027 in the court of Judge Jeffrey M. Brown.

The legal matter delayed work by about six weeks, Knerr said, which pushed the project closer to winter.

Complete General argues in its lawsuit that its bid met all of the requirements set by the county and that the Suburban Maintenance bid did not meet the requirement for 10% “Small Business Enterprise” involvement in the project. Further, Complete General says that county officials met with Suburban Maintenance about its bid without other bidders being present, which it says is a violation of state regulations for the bidding process.

“Despite being bound to look out for the best interest of the Licking County taxpayers, the (board of county commissioners) failed to exercise sound discretion when it violated (state regulations) and improperly held an in-person, ex-parte evidentiary proceeding with Suburban Maintenance where competing bidders were excluded from attending,” Complete General’s attorneys wrote in the lawsuit.

Licking County Administrator David Edelblute said when the lawsuit was filed that ODOT officials had said the process did not violate state regulations.

Alan Miller writes for TheReportingProject.org, the nonprofit news organization of Denison University’s Journalism program, which is supported by generous donations from readers. Sign up for The Reporting Project newsletter here.