The Licking County Planning and Development staff report recommends approval of a preliminary plan for a proposed Meta data center in Jersey Township – with 14 conditions that include the prohibition of fracking and the use of groundwater for cooling, restrictions on noise levels from equipment, and limitations on hours for testing backup generators.

Another condition would require a decommissioning plan if and when the facility would be shut down in the future. 

The proposed 620,000-square-foot facility will be on the agenda when the Licking County Planning Commission meets tonight, Monday, Nov. 23.

Meta already has built or is building at least 20 data center buildings on two large sites on the north and south sides of the New Albany International Business Park, but this is the first one east of New Albany in unincorporated Jersey Township. 

If approved, the data center would be next door to and powered by the 500 megawatt, gas-fired Neo Power power plant proposed by Will-Power Ohio and under consideration by the Ohio Power Siting Board (case number 26-0627-EL-BGN).

The planning commission will meet at 6 p.m. tonight in the basement of the Licking County Administration Building, 20 S. 2nd St. in downtown Newark.

This page of the Meta plan shows the footprint of the Meta data center proposed for Mink Street. The gray area to the right of the data center site is for a proposed 500 megawatt power plant to provide electricity to the data center.

The 350-acre site owned by a Meta subsidiary and proposed for the new data center and power plant is east of Mink Street, south of Jug Street and north of Rt. 161 and Beaver Road NW.

The staff report says that on Oct. 23, the commission approved the replat of “Hodge Estates,”  which consolidated properties to create the site for both the data center and power plant. In June of 2025, the commission provided a non-binding recommendation for approval of a proposed amendment to Jersey Township’s zoning map, and in July 2025, township trustees approved the change that allowed data centers as a permitted use within the “Innovation Employment District.”

The proposed data center would be built on about 200 of the 350 acres that are currently agricultural land and home sites.

“Staff finds that the proposed use and accessory components are permitted by township zoning within the Innovation Employment (IE) District Overlay,” Licking County Planning Director Carson Combs wrote in the staff report to the planning commission.

| Read more: Meta data center proposal on Monday agenda for Licking County Planning Commission

Combs wrote that the preliminary plan for the proposed data center development generally meets the county’s criteria for major subdivisions.

“The proposed plans, with added conditions, will conform to the basic requirements for subdivisions and the approved township zoning overlay and will provide for the orderly development of infrastructure,” Combs wrote. “As amended, the proposed plan will provide for the public health, safety, convenience, and general welfare of Licking County.”

Based upon those findings, the staff recommended approval of the preliminary plan with the following conditions:

1. That road and drainage improvements along Jug Street are completed in conjunction with construction to address future traffic and stormwater impacts, to the satisfaction of the Licking County Planning Commission (LCPC) and County Engineer;

2. That required wetland buffers and easements are provided and that pre-and post- construction study of all “Category 3 wetlands” on the site are conducted to the satisfaction of the Licking County Soil & Water Conservation District;

3. That stormwater design is managed to limit impacts to the South Fork of the Licking River Watershed, and that any watershed alterations are addressed to the satisfaction of staff;

4. That disconnected field tiles are addressed to the satisfaction of the County engineer and LCPC;

5. That an Operations and Maintenance (O&M) agreement, including required easements, is approved and recorded with the county;

6. That the applicant adheres to all aspects of an approved Road User Maintenance Agreement (RUMA), that a TIS is completed and approved, and that all identified transportation improvements are made as part of the development, to the satisfaction of the LCPC and the County Engineer;

7. That the use of groundwater for cooling needs is prohibited to protect area aquifers, and that no groundwater permits from the State of Ohio are permitted for the site;

8. That an agreement is approved between the Licking Regional Water District for public water and sewer provision that addresses water usage and parameters for the discharge of waste;

9. That fracking, subsurface waste injection or discharging of waste into surface waters or the stormwater system are prohibited;

10. That an emergency response plan is approved by the fire district prior to operation and that any necessary resources (including equipment, training and manpower) are provided by the applicant;

11. That sound monitoring is provided that demonstrates noise levels no greater than 55 dBA mid-range decibel frequencies and 55 dBC low-range, or bass frequencies, for nearby residential properties;

12. That generators are restricted to outages, emergencies and daytime testing Monday through Friday between the hours of 9 a.m. and 5 p.m. and not for the support of grid operations;

13. That a decommissioning plan is approved by the county with an appropriate bond for the site, subject to staff approval; and

14. That all necessary landscaping and screening details as outlined in this report are finalized in conjunction with construction plan review, subject to staff approval.

The preliminary site plan was filed with the Licking County Planning and Development office by Sidecat LLC, the land acquisition and development arm of Meta, the parent company of social media applications Facebook, Instagram, WhatsApp and Threads.

The Meta site for the proposed data center includes a dozen wetlands of various sizes, two ponds and a stream the company proposes to remove, according to the site plan filed with Licking County.

The staff report notes that the planning commission’s role in such projects is to review the proposed preliminary plan for conformance to the Licking County Subdivision Regulations, and “the commission has the power to approve plans if determined to be in the public interest and may attach conditions as it deems necessary to meet the objectives of these regulations.” 

The board may determine, after weighing applicable factors, whether the applicant has met the standards set forth by the regulations based on several general criteria. Those criteria include meeting all requirements in the county regulations, providing orderly development of public and private infrastructure while minimizing harm, protecting natural resources and minimizing flooding, and providing for the public health, safety, convenience, and general welfare of Licking County.

Of the 259 data centers proposed, under construction or in operation in Ohio, 135 are in central Ohio and 52 of them are in Licking County, according to Data Center Map, which tracks data centers around the world. Most of the Licking County facilities are in the New Albany International Business Park.

| Read more: Public hearing draws some support and plenty of opposition to 500-megawatt power plant for data center

The Will-Power power plant, if approved, is expected to emit the following pollutants, according to the company’s air-pollution permit application to the Ohio Environmental Protection Agency:

3,471,813 tons of greenhouse gas pollution, 197.1 tons of fine particulate matter, 243.3 tons of Nitrogen Oxides (NOx), 172.73 tons of Volatile Organic Chemicals (VOCs), 189.1 tons of Sulfur Dioxide (SO2), 245.2 tons of Carbon Monoxide (CO) and 40,200 pounds of Hazardous Air Pollutants (HAPs).

Will-Power is a subsidiary of the Williams companies, a natural gas company based in Tulsa, Oklahoma.

Alan Miller writes for TheReportingProject.org, the nonprofit news organization of Denison University’s Journalism program, which is supported by generous donations from readers. Sign up for The Reporting Project newsletter here.