Yet another data center proposed by Meta for western Licking County will be on the agenda for consideration by the Licking County Planning Commission on Monday, Nov. 23.
Meta already has built or is building at least 20 data center buildings on two large sites on the north and south sides of the New Albany International Business Park, but this is the first one east of New Albany in unincorporated Jersey Township.
If approved, the data center would be next door to and powered by the 500 megawatt, gas-fired Neo Power power plant proposed by Will-Power Ohio and under consideration by the Ohio Power Siting Board (case number 26-0627-EL-BGN).
The planning commission will meet at 6 p.m. on Nov. 23 in the basement of the Licking County Administration Building, 20 S. 2nd St. in downtown Newark.
The 350-acre site owned by a Meta subsidiary and proposed for the new data center and power plant is east of Mink Street, south of Jug Street and north of Rt. 161 and Beaver Road NW.
| Read more: Public hearing draws some support and plenty of opposition to 500-megawatt power plant for data center
The preliminary site plan was filed with the Licking County Planning and Development office by Sidecat LLC, the land acquisition and development arm of Meta, the parent company of social media applications Facebook, Instagram, WhatsApp and Threads. It calls for a “620,000-square-foot data center facility and associated uses.”
The Meta site for the proposed data center includes a dozen wetlands of various sizes, two ponds and a stream the company proposes to remove, according to the site plan filed with Licking County.

Of the 259 data centers proposed, under construction or in operation in Ohio, 135 are in central Ohio and 52 of them are in Licking County, according to Data Center Map, which tracks data centers around the world. Most of the Licking County facilities are in the New Albany International Business Park.
The Will-Power power plant, if approved, is expected to emit the following pollutants, according to the company’s air-pollution permit application to the Ohio Environmental Protection Agency:
3,471,813 tons of greenhouse gas pollution, 197.1 tons of fine particulate matter, 243.3 tons of Nitrogen Oxides (NOx), 172.73 tons of Volatile Organic Chemicals (VOCs), 189.1 tons of Sulfur Dioxide (SO2), 245.2 tons of Carbon Monoxide (CO) and 40,200 pounds of Hazardous Air Pollutants (HAPs).
Will-Power is a subsidiary of the Williams companies, a natural gas company based in Tulsa, Oklahoma.
Alan Miller writes for TheReportingProject.org, the nonprofit news organization of Denison University’s Journalism program, which is supported by generous donations from readers. Sign up for The Reporting Project newsletter here.